Key Strategies for Mitigating and Accelerating Project Schedules

  • Writer: Logikheim
    Logikheim
  • Jun 19, 2024
  • 3 min read

Updated: Oct 19, 2024


Challenges to project timelines are almost inevitable in the fast-paced world of project management. Whether it’s delays, resource shortages, or unforeseen obstacles, these issues often demand targeted interventions. In some cases, mitigating delays or implementing acceleration measures becomes essential. To tackle these challenges effectively, it’s important to employ a structured approach that carefully considers the best strategies for keeping the project on schedule.


Assessing the Current State

When a project is already in progress and facing scheduling issues, the first step is to thoroughly assess the current project status. This involves reviewing the project schedule, identifying critical paths, and understanding the root causes of delays or potential risks. Engaging with key stakeholders, project teams, and resource managers to gather comprehensive insights into the project's challenges is crucial. This assessment provides a clear picture of where interventions are needed and which areas require immediate attention. It also helps to critically evaluate the program, uncovering any errors in logic and assumptions that may be affecting the schedule.


Recovery and Acceleration Strategies

Based on the GAO-16-89G Schedule Assessment Guide, several key strategies can be employed to recover from schedule variances and accelerate project timelines:


1. Crashing

Crashing involves adding resources to time-dependent activities to complete work faster. This technique can be effective for reducing project duration, but it requires careful management to avoid additional costs and potential quality issues. When implementing crashing, it's important to consider the impact on budget and quality, ensuring that the increased resources do not compromise the project’s objectives.


2. Fast Tracking

Fast tracking entails reducing sequential dependencies between activities to allow for parallel work. This approach can accelerate the project schedule but may introduce risks if tasks that are ideally performed in sequence are executed concurrently. Careful planning is needed to manage resource allocation and quality, as well as to address any potential risks associated with overlapping activities.


3. Splitting Long Activities

Splitting long activities into shorter, manageable tasks that can be worked in parallel is another effective acceleration strategy. This method can help streamline the project timeline but may lead to resource over-allocation. It’s important to balance the split tasks to prevent bottlenecks and ensure that parallel activities are effectively managed.


4. Reviewing Constraints and Lag Assumptions

Reassessing assumptions related to constraints and lags can help in adjusting the project schedule. If certain constraints or lags are no longer justified, removing or modifying them can help in accelerating the project. However, this should be done cautiously, ensuring that any changes are realistic and do not introduce new risks.


5. Adding Overtime and Reducing Non-working Periods

Increasing work hours through overtime or reducing non-working periods can speed up project

completion. This approach can be effective for addressing immediate schedule pressures, but it can lead to increased costs and potential declines in team morale. Careful management of overtime is crucial to balance cost, quality, and team well-being.


6. Reducing Scope

Decreasing the project scope can shorten both duration and costs, especially if some requirements are deemed less critical. However, it is important to consider the impact on the project's overall objectives and deliverables. Ensuring that any scope reductions do not undermine the project’s primary goals is essential.


7. Reviewing Duration Estimates

Revisiting duration estimates based on actual progress records can help in refining the schedule. Accurate duration estimates based on up-to-date data can provide a more realistic view of the project timeline and help in making necessary adjustments.


8. Allocating Contingency

Using contingency reserves can help absorb delays and mitigate risks. Allocating contingency in accordance with identified risk mitigation plans can provide a buffer for unexpected issues. However, using contingency too early in the project may reduce the likelihood of completing the project on time if unforeseen risks arise later.


Documenting Changes

Regardless of the combination of methods used for acceleration or recovery of variances, it is crucial to document the changes made to the schedule. Archiving the original schedule and documenting the techniques and adjustments applied will provide a clear record for future reference. Recalculating and assessing the critical path for reasonableness ensures that the modifications are effective and aligned with the project’s objectives.


Conclusion

Mitigating and accelerating project schedules requires a strategic and adaptive approach. By assessing the current status, implementing targeted delay mitigation strategies, and employing acceleration measures, project managers can address scheduling challenges effectively. Techniques such as crashing, fast tracking, and splitting long activities, along with other strategies, offer ways to navigate complex project timelines. In addition, effective communication, resource optimization, and proactive monitoring are key components in managing the intricacies of project schedules and achieving successful project outcomes.


References: GAO. (2016). Schedule Assessment Guide: Best Practices for Project Schedules. GAO-16-89G.

Logikheim Logo.webp

Advanced Project Solutions

CONTACT US

Reach out with any
questions or inquiries

Thanks for submitting!

ADDRESS

Sydney, NSW

PHONE

0487 325 475

EMAIL

  • Facebook
  • LinkedIn
  • Twitter

© 2024 Logikheim
 

bottom of page